Tam Quang Minh manufactured and installed wooden guest room furniture at Taishi Hotel & Apartment, 62 Ho Nghinh, Da Nang.

Key points
- Scope: Wooden guest room furniture
Contract and schedule
The contract was signed in October 2022 and covered the full cycle: site survey and measurement, design, production and installation of the wooden interiors. The agreed schedule was 150 working days, with completion planned for April 2023.
Materials
At the owner’s request, all carcasses were made from An Cuong moisture-resistant green-core MDF, a board suited to Da Nang’s coastal humidity.
How we work
- Survey and measurement of each room type
- Design and approval before production
- Factory production and quality checks
- Installation and handover by our own team
All joinery is produced at our own factory in Xuan Phu, Da Nang: panel cutting, CNC machining, edge banding, assembly and finishing, with checks at each stage before the goods leave for site. Installation is carried out by our own team, so the people who build the furniture are accountable for how it fits.
Shop drawings, measured acceptance and a 12-month warranty
Before any panel was cut, our team issued shop drawings showing the dimensions, finishes and design intent of each piece, and the owner approved them. Production started only after that sign-off, so changes were settled on paper rather than on site.
Acceptance was based on measured quantities. After installation, both sides measured the work actually installed and settled it against the unit rates agreed in the contract appendix. A Tam Quang Minh site supervisor was responsible for progress and quality on site, and the rooms were cleaned and handed back clear of debris.
The furniture is covered by a 12-month warranty from handover. Defects such as warping, cracking or workmanship faults are repaired at our cost, and inspection starts within three days of the owner’s notice.
Project photos






On-site photos taken during and after the works. Photos: Tam Quang Minh
Project summary
Taishi Hotel & Apartment, 62 Ho Nghinh, Da Nang: Tam Quang Minh delivered wooden guest room furniture.
Related service: Hotel interiors in Da Nang.
Planning a similar project or an export order? See our manufacturing capabilities and product range, or request a quote.
Project Q&A
What did Tam Quang Minh deliver at Taishi Hotel & Apartment, 62 Ho Nghinh, Da Nang?
The full cycle for the wooden guest room furniture: site survey and measurement, design, production at our Xuan Phu factory and installation by our own team, using moisture-resistant green-core MDF.
How long did the project take?
The contract set 150 working days, from October 2022 to a planned completion in April 2023.
What warranty applies to the furniture?
Twelve months from handover. Repairs for warping, cracking or workmanship faults are made at our cost, starting within three days of notice.